Registration of applications to Granting permission for execution of work involving following steps: 1) Registration of Application 2) Joint feasibility survey & Report 3)Preparation of abstract estimate and demand of Plan & Estimate (P&E) charges from party 4) Deposit ofP&E charges byparty 5)Preparation of Plan , signature and approval 6) Preparation of Detailed Estimate , signature vetting and approval 7) Administrative approval of Divisional Railway Manager 8) Advice to Party for deposition of way leave charges. 9) Deposit of Way leave charges by the Party 10) Signing of agreement by the Party 11) Application for Commissioner of Railway Safety (CRS) Sanction( if required) 12) Receipt of CRS sanction (if required) 13) Permission for execution of work |