                                                               4.0 WAY LEAVE PROPOSAL

Sl.  No.

Service

Time limit

Single Window Agency

 (to be contacted for)

4.1

Only on line application are accepted

Customer to apply online

  Web Portal : https://iricep.gov.in/WLRMS/ 

4.2

Submission of signed copy of duly filled printed application form, from web portal along with applicable Registration fee (Demand Draft/Money Receipt), Draft copy of agreement duly signed on each page and sketch plan of site to Division. Action to be taken by the Applicant.

As soon as possible

  Sr. Divisional Engineer  (Co-ordination) 

 Adra Division

crownshrikant@yahoo.com /

srdenco@ada.railnet.gov.in

Chakradharpur Division

srdencoord.ckp@gmail.com / srdenco@ckp.railnet.gov.in

 Kharagpur Division

srdencokgp1@gmail.com / srdenco@kgp.railnet.gov.in

 Ranchi Division

srdencornc@gmail.com /srdenco@rnc.railnet.gov.in

6.3

Registration of applications to Granting permission for execution of work involving following steps:

1) Registration of Application

2) Joint feasibility survey & Report

3)Preparation of abstract estimate and demand of Plan & Estimate (P&E) charges from party

4) Deposit ofP&E charges byparty

5)Preparation of Plan , signature and approval

6) Preparation of Detailed Estimate , signature vetting and approval

7) Administrative approval of Divisional Railway Manager

8) Advice to Party for deposition of way leave charges.

9) Deposit of Way leave charges by the Party

10) Signing of agreement by the Party

11) Application for Commissioner of Railway Safety (CRS) Sanction( if required)

12) Receipt of CRS sanction (if required)

13) Permission for execution of work

Depends on the case(As multiple actions involved by the Party and by the Railway )

  Sr. Divisional Engineer  (Co-ordination) 

 Adra Division

crownshrikant@yahoo.com /

srdenco@ada.railnet.gov.in

Chakradharpur Division

srdencoord.ckp@gmail.com / srdenco@ckp.railnet.gov.in

 Kharagpur Division

srdencokgp1@gmail.com / srdenco@kgp.railnet.gov.in

 Ranchi Division

srdencornc@gmail.com /srdenco@rnc.railnet.gov.in

6.4

Completion of work by the Party

As per scope of work

6.5

Applications involving CRS sanction(Item no.11&12 of 6.3).

Additional 60 days over 6.3

  Chief Bridge Engineer 

cbe@ser.railnet.gov.in 




 





Source : South Eastern Railway CMS Team Last Reviewed : 21-11-2016  


  Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.